
Work on the station facade, including a magnificent entrance porch, is almost complete under the Amrit Bharat Station Scheme (ABSS) of Mangaluru Junction Railway Station under Southern Railway’s Palakkad Division, in Mangaluru on March 20, 2025.
| Photo Credit: ANIL KUMAR SASTRY
Achieving over 80% physical progress in the development work under Amrit Bharat Station Scheme (ABSS) at Mangaluru Junction (MAJN) Railway Station, Southern Railway’s Palakkad Division is confident of completing all the sub-work before April 2025.
MAJN was among the four stations in Dakshina Kannada included under ABSS for development at an estimated cost of ₹19.32 crore following efforts by the then MP Nalin Kumar Kateel. Prime Minister Narendra Modi and Railway Minister Ashwini Vaishnaw had virtually inaugurated ABSS works across the country on August 6, 2023.
Circulating and parking area

Works on the station facade, parking and circulating area are almost complete under the Amrit Bharat Station Scheme (ABSS) at Mangaluru Junction Railway Station under Southern Railway’s Palakkad Division in Mangaluru.
| Photo Credit:
ANIL KUMAR SASTRY

Work on the magnificent entrance porch is almost complete at the Mangaluru Junction Railway Station.
| Photo Credit:
ANIL KUMAR SASTRY
Widening of clogged approach roads to MAJN, from Naguri and Padil, both connecting Mangaluru-Bengaluru National Highway 75, were in advanced stages of completion when The Hindu visited the station on Friday (March 20, 2025). Nearly 7,000 sqmt expansive circulating area in front of the station entrance was concreted and beautified to facilitate vehicular movement, dropping and picking of passengers. A large 1,632 sqmt parking area for four-wheelers and two-wheelers was also nearing completion. Physical progress of these two sub works was pegged at 89% by officials.
Progress of work in Mangaluru Junction under Amrit Bharat Station Scheme
Name of the work | Physical progress |
Road work | 89% |
Parcel office | 72% |
Station elevation | 79% |
Entrance arch | 75% |
AC waiting hall | 60% |
Additional platform cover | 79% |
Telecom works | 95% |
Electrical works | 100% |
Tentative date of completion for all works is March 31, 2025
**Source: Palakkad Division, Southern Railway
Traditional architecture
The new entrance porch spanning 155 sqmt was almost complete adding beauty to the station and facilitating hassle-free entry and exit for passengers with 75% physical progress. Work on a 176 sqmt air-conditioned waiting hall and 11 sqmt restroom for disabled passengers too was under progress with 60% progress.
Traditional coastal architecture could be seen on the station facade that was being given a new look. Nearly 75% of the work was complete as on date. Work on one more 6 metre-wide foot overbridge connecting Platform 1 and Platforms 2-3 in addition to the existing three was fast progressing.
Platform shelters
Platforms 1, 2 and 3 (3,048.33 sqmt) were being resurfaced while full-length platform shelters were being provided for all the three platforms. Pillars were being erected to provide additional covers on these platforms. The platforms would also be provided with high mast lights, BLDC fans, mobile phone charging units and such other amenities to enhance passenger convenience.
Palakkad Divisional Railway Manager Arun Kumar Chaturvedi told The Hindu that the Division was confident of completing the ABSS Phase 1 works before April. As on date, 75% of financial progress too was achieved, he added.

Pillar work for providing full-length platform shelter on Platforms 2 and 3 in progress under the Amrit Bharat Station Scheme (ABSS) at Mangaluru Junction Railway Station.
| Photo Credit:
ANIL KUMAR SASTRY

Vehicular parking and circulating area works are almost complete under the Amrit Bharat Station Scheme (ABSS) at Mangaluru Junction Railway Station under Southern Railway’s Palakkad Division in Mangaluru.
| Photo Credit:
ANIL KUMAR SASTRY
As a transit hub, MAJN established on May 20, 1979, facilitates movement of 35 trains witnessing more than 6,700 passenger footfalls daily. The Junction connects various regions, including Kerala to the South, Maharashtra/Goa and the New Mangalore Port to the North and Bengaluru-Chennai to the East.
Published – March 23, 2025 03:16 pm IST
Source:https://www.thehindu.com/news/cities/Mangalore/palakkad-division-confident-of-completing-mangaluru-junction-station-development-work-by-april/article69364574.ece